Article

Cladding claims and insurance liability caps

Insight shared by:

Gateley Legal

Article by

The recent decision in Manchikalapati v Zurich demonstrates that in terms of claims to remedy cladding, the courts are unlikely to be sympathetic to insurers trying to limit their liability to pay for remedial works by relying on narrow interpretations of liability caps.

Overview

The problems with the fire safety measures at high-rise apartments which were uncovered, tragically, by the Grenfell Tower fire have resulted in a need for extensive and expensive remedial works. This has in turn cast a spotlight on the previously rarely-visited aspect of insurance policies: the liability cap. 

Moreover, a spate of recent insolvencies in the construction industry, coupled with the urgency of remedying these defects, has led to the tenants, owners and insurers of high-rise apartments being increasingly faced with the prospect of meeting the cost of multi-million-pound defects claims related to cladding and fire safety. 

The recent case of Manchikalapati v Zurich [1] represents a  landmark decision on the law in this area. In this case the owners of flats in one of these blocks, faced with a defects bill as high as the cost of the block itself, brought a claim against their structural warranty provider, which in turn sought to limit their recovery through an extremely narrow reading of its own policy.  

Background

The claimants were the owners of almost a third of the flats in a block in Manchester called New Lawrence House. The defendant, a well-known insurer of new homes, provided a 10-year structural defects insurance policy to each flat owner. 

The dispute concerned the interpretation of the policy’s maximum liability clause, which provided:

 “for a New Home which is part of a Continuous Structure, the maximum amount payable in respect of the New Home shall be the purchase price declared to Us subject to a maximum of £25 million.

Where the combined value of all New Homes within a Continuous Structure exceeds £25 million, the total amount payable by Us in respect of all claims in relation to the New Homes and the Continuous Structure shall not exceed £25 million.”

What this effectively meant was that the maximum that the owner of each unit in the development could claim under the policy was the value of that unit, subject to a maximum figure calculated by apportioning the sum of £25 million between each flat in the development.

The dispute

At trial, it was determined that the Zurich policy would respond to the claimants’ extensive defects claims, with the dispute centring around the maximum sum the claimants were entitled to.

Zurich successfully argued that the policy liability cap limited the value that each claimant could claim to the cost of their respective unit. The bill to rectify the defects came to £9.7million, but the value of the flats owned by the claimants was only £3.364 million. This left a shortfall of over £6 million.

Furthermore, the total value of all flats in New Lawrence House was £10.85 million but only one in every three flat owners had joined the claim, despite each flat owner standing to benefit from the defects being resolved. The claimants appealed.

The claimants argued at appeal that a claim relating to common parts should not be capped by the aggregate value of the units the claimants owned, but by the aggregate value of all the units in the block. This  would bring their claim fully within the value of the policy and would have been the result, had each flat owner joined the claim. 

Zurich, meanwhile, cross-appealed on a number of technical points relating to interpretation of the policy, such as that the claimants should only be able to claim for sums already spent, rather than future costs, and that claims against third parties should have been fully exhausted before the policy would respond.

The decision

The Court found in favour of the claimants and rejected Zurich's cross-appeals. The Court described Zurich’s interpretation of its own policy as “a strained and artificial construction” which would mean that the circumstances required for Zurich to pay out would be extremely remote, so much so that it would be almost impossible for the policy holders to meet the threshold required in order for the policy to respond. The policy's maximum liability cap was the aggregate value of the entire block, and not the aggregate value of the flats owned by the claimants.

What can we learn from this case?

  1. Cladding problems have made the prospect of an insurer's structural defects liability limit being reached a very real possibility, and it is important for both developers and purchasers of these flats to know that the Court has rejected attempts to construe this limit narrowly.
  2. Owners and developers of flats affected by cladding issues should be prepared for insurers to challenge their claims on technical grounds or otherwise try to narrow the scope of the insurance policy where possible. If this does happen, the Courts appear likely to be sympathetic towards policyholders, and inclined to take a “common sense” approach to the construction of these clauses. 
  3. Given the intense media scrutiny of these issues, fire safety and robust insurance policies are being increasingly prioritised by prospective purchasers, so it will be crucial to understand how the structural warranty operates, particularly in relation to the liability limit.  

 [1] Manchikalapati and others v Zurich Insurance plc (t/a Zurich Building Guarantee & Zurich Municipal) and others [2019] EWCA Civ 2163

Gateley Plc is authorised and regulated by the SRA (Solicitors' Regulation Authority). Please visit the SRA website for details of the professional conduct rules which Gateley Legal must comply with.

Got a question? Get in touch.