Article

Recovering overpayments in construction contracts

Insight shared by:

Gateley Legal

Article by

In Grove v S&T, Coulson J decided that an employer can commence an adjudication to determine the true value of an interim application. This is notwithstanding that a separate adjudication has determined the amount certified as due.

This case has been heralded as an opportunity for employers. If they consider that an overpayment has been made in the first adjudication, they can potentially have this remedied within a second adjudication. This decision however leaves some ambiguity over how this repayment mechanism works in practice in respect of interim applications.

Traditionally if the employer considers that they have made an overpayment in respect of an interim application, they can seek to recover this money either upon the next interim application (assuming one is made by the contractor) or by way of reconciliation at the Final Account. However, both options mean that the employer will have already made the overpayment to the contractor and will have to wait to recover the monies (whilst bearing the risk that the contractor may go insolvent in the meantime). This is why this judgment has been welcomed by employers, as it provides them with another opportunity to recover an overpayment from the contractor (potentially before the next interim application or final account), by way of a second adjudication.

However in JCT contracts, there is no contractual mechanism for the employer to recover monies upon an interim application. The case concerned JCT Design and Build 2011, which states that in interim applications it is the employer who must serve a Pay Less Notice (4.9.4) and make payment[1]. Comparable wording also exists for interim payments under the 2016 JCT contract suite. JCT contracts therefore do not make provision for the contractor to make payment to the employer, except in respect of the final payment.

Coulson addressed this point by claiming that the employer’s entitlement to recover the overpayment is either by way of an implied mechanism in the contract or by way of restitution. He stated that: “I can see no need for the interim payment provisions to deal expressly with what happens when or if an adjudicator decides that, on this premise, an employer is entitled to recover an overpayment. The adjudicator has decided that there has been an overpayment and pursuant to the contractual obligations to comply with the adjudicator’s decision, the contractor must therefore repay the excess … it is simply an adjustment – justified on the basis of implied terms or restitutionary principles – to the existing contractual mechanism.”[2]

Despite this explanation, there is likely to be continued debate on whether or not repayment mechanisms (from the contractor to the employer) should be implied into the contract. Although the repayment mechanism on interim applications is not dealt with in JCT contracts, it is dealt with in NEC4, which states: “A payment is made by the Contractor to the Client if the change reduces the amount due.”[3] This seems to raise the question that it is a matter on which the parties should agree upon. It is more usual in the court’s interpretation of contracts to hold the parties to account for what they have bargained for by way of commercial agreement. The approach taken in this case appears to be contrary to the court’s general reluctance to step in and grant implied terms. Coulson cited the Supreme Court decision in Aspect v Higgins as authority for implying a repayment term within the contract. However, in this case a repayment term was implied into the Scheme[4], rather than to the parties’ commercial agreement. Employers would be wise to exercise caution while this case continues to cause some debate.

In the meantime, this case reaffirms simple best practice for employers to always make sure your Payment Notice and Pay Less Notices are served accurately and in time. This is still the best way to avoid the complexities arising from recovering an overpayment.

[1] The same difference in terminology for interim and final payments is used in clause 4.9 of the JCT Design and Build 2016.

[2] Paragraph 135 of the judgment.

[3] Clause 51.1 of the Engineering and Construction Contract.

[4] Scheme for Construction Contracts (England and Wales) Regulations 1998.

Gateley Plc is authorised and regulated by the SRA (Solicitors' Regulation Authority). Please visit the SRA website for details of the professional conduct rules which Gateley Legal must comply with.

Got a question? Get in touch.