Kwasi Kwarteng, the Secretary of State for Business, Energy & Industrial Strategy, has refused consent for a development consent order (“DCO”) under the Planning Act 2008 intended to develop £1.2bn of electricity interconnector infrastructure across England by Aquind Limited.

Aquind proposed to install an interconnector, alongside its private commercial telecommunications cables, under the English Channel and through Portsmouth before terminating these at a principal Converter Station located on private farmland in Hampshire.

Who objected to the scheme and why?

Gateley Hamer was instructed by the host authority, Portsmouth City Council, who objected to the scheme on the basis of the detrimental impacts the scheme would have on the local (and strategic) road network, impacts it would have had on playing fields, and the compromising of programmed sea defence works required to protect the City. Gateley Hamer’s Managing Director, Jonathan Stott also represented the landowners for the principal converter station, and businesses impacted by the scheme by Piers Collacott. 

Aquind applied for compulsory acquisition powers for the land required to deliver the scheme within the DCO.

Gateley Hamer raised technical objections during the examination challenging the application for compulsory acquisition powers, arguing the case for compulsory acquisition powers had not been made. 

The challenges included the inclusion of spare capacity (commercial) fibre optic cables as part of the application for powers (resulting in land being included in the Order for which powers should not have been applied for as the apparatus should have been outside of the scheme), failure to fully consider alternatives, and failure to make an assessment of public benefit versus private loss in the assessment of alternatives.

Secretary of State's decision

The Secretary of State consulted on these specific points and agreed with the arguments put forward by Gateley Hamer in refusing the consent for the scheme.

To find out more about our infrastructure development team and how they can facilitate or object to the implementation of DCOs, please get in touch or visit our infrastructure development page for more information about our services.

Learn more about how we can help with infrastructure development

If you would like any support or guidance on DCO's or infrastructure development, please get in touch with our experts or for more information on our services, please visit our infrastructure development page.