The case of Laing O'Rourke Delivery Limited v Shepperton Studios Limited [2026] EWHC 612 (TCC) is another instance where the Technology and Construction Court has allowed an insolvent company, Laing O’Rourke Delivery Limited (LOR), to enforce an adjudication decision made in its favour (in this case, against Shepperton Studios) so long as suitable measures are put in place to allow the award to be recouped by the paying party upon final determination.
Background
The claim involved a dispute between the parties over an interim payment application. LOR (the contractor) issued the application, for £5,627,275.11 to Shepperton (the employer), and Shepperton responded with:
- A payment notice confirming they intended to pay £2,420,516.84 of LOR’s notified sum; and
- A payless notice confirming they were applying a total of £2,428,514.47 in further deductions to the (already reduced) sum in the interim payment notice.
The effect of these two notices was that nothing was due to LOR in respect of its application.
LOR subsequently commenced an adjudication on this dispute. The adjudicator found that Shepperton’s payment notice was invalid as it had failed to provide a breakdown for how the notified sum was reached, as was required by the contract. He also found the payless notice was invalid as it adopted the notified sum in the (invalid) payment notice as a starting point. He awarded LOR the full sum claimed in its payment application.
Enforcement proceedings
LOR subsequently sought to enforce the adjudication decision via the TCC’s expedited summary judgment process. Shepperton raised both substantive and procedural arguments to resist this. This included arguments about the validity of its notices, and also a request that:
‘There should be a stay [of execution] on any sums payable. LOR is insolvent. LOR now continues to trade only by the support, continued from time to time, of its parent.’
This was requested due to Shepperton’s concern that, if it paid the sum awarded by the adjudicator and then was successful in any final determination of the payment dispute (e.g. court proceedings), it would not be able to recover the sums paid to LOR due to LOR’s insolvency. This is a common concern for those facing adjudication enforcement proceedings brought by insolvent parties.
The Court’s decision
The judge granted summary judgment in LOR’s favour for £3,198,660.64. This was the difference between the £5,627,275.11 sought by LOR and the deductions identified in Shepperton’s payless notice.
In terms of the requested stay of execution, the judge appeared to accept that LOR was in financial difficulty and, as a result, a stay was the correct starting position (Wimbledon v Vago [2005] EWHC 1086 (TCC)). However, the Court felt able to depart from this position because Shepperton had received a: