The case of One Hyde Park Ltd v Laing O’Rourke Construction South Ltd in the Technology and Construction Court concerns significant construction defects at a luxury 2011 residential development in Knightsbridge, London.
Mrs Justice Jefford awarded £35m for the claimant, One Hyde Park Ltd (OHP), following the dramatic withdrawal of the defendant, Laing O’Rourke Construction South Limited (LOR SL), just over two weeks before commencement of the final trial. LOR SL was placed into voluntary liquidation by resolution of its sole shareholder, Laing O’Rourke plc, shortly after.
It’s also important to consider what other remedies may now be available to OHP in light of LOR SL’s insolvency.
Background
The claim focused on four primary defects, the most significant of which (£34.5m) involved widespread “ants’ nest” corrosion in copper pipework. Other alleged defects included butterfly valves which failed to close properly, preventing maintenance, the existence of multiple leaks in the heating pipework due to workmanship failures in soldered joints, and a specialised cradle used for cleaning and maintaining the penthouse facades which had failed to operate correctly since completion.
15 days before the commencement of the final trial on 27 February 2025, LOR SL’s solicitors informed the Court that its parent company and sole shareholder, Laing O’Rourke plc, had withdrawn financial support. It subsequently resolved to place LOR SL into creditors’ voluntary liquidation.
Despite the parent group’s significant revenue (FY24 results show group revenue of £4bn, net assets of £218.7m, and an order book of £11.9bn), it “pulled the plug” on the subsidiary, a move the Judge described as “commercially amoral” given the protracted prior negotiations and LOR SL’s full participation in the litigation until that point.
While the Court struck out LOR SL’s defence, OHP was still required to prove its case to the Court’s satisfaction. As LOR SL did not attend or call its witnesses, its served factual and expert evidence was deemed to have no status. The Court relied on OHP’s expert and factual evidence, unchallenged.
Contractual responsibility and loss
A central issue in the case was whether OHP, as the freeholder and manager, was responsible for the repairs and had suffered the losses claimed in the proceedings. LOR SL had argued that individual tenants were responsible for pipework exclusively serving their apartments.
The Court examined the complex leasehold structure, including the superior lease and individual underleases. Mrs Justice Jefford concluded that the chilled water pipework constituted a “single, continuous distribution system” providing common services to the entire complex. Evidence showed that isolating individual apartments could lead to stagnant water and bacterial infestation, reinforcing that it was a unified system maintained by the landlord. Accordingly, the Court concluded that OHP held the maintenance obligation and the right to claim damages.
Even if the primary case had failed, the Judge decided that the claimant could have recovered losses in any event, for the benefit of tenants under the “narrow ground” established in St Martin’s Property Corporation Ltd v Sir Robert McAlpine Ltd.
Quantum of loss
The Court accepted the assessments of OHP’s quantum expert, awarding the full revised sums for each defect, totalling over £35m, finding that OHP had successfully proved LOR SL’s breaches of the Main Contract and the 2010 Collateral Warranty.
Recovery challenge and BLOs?
As LOR SL is in voluntary liquidation, OHP faces a challenge in recovering the judgment damages awarded to it. In a statement following the judgment, OHP described it as a “decisive victory”:
“… the residents have indicated that they will continue to pursue all available legal and commercial avenues to recover their losses … We are committed to ensuring Laing O’Rourke is held fully accountable and makes full and fair payment for the construction defects it has been found responsible for.”
The Building Safety Act 2022 (BSA) provides various wide-ranging remedies to enable parties to recover costs relating to building safety defects. One such measure under s.130 enables a High Court to make what is called a ‘Building Liability Order’ (BLO). The High Court can make a BLO where it is “just and equitable” to do so, against a corporate entity which is or has been “associated” with the party at fault. In principle this can apply to the present scenario where a claimant could seek a BLO against another group company if the original entity was in liquidation.