In Davies & Davies Associates LTD v Steve Ward Services (UK) LTD (Technology and Construction Court, Roger ter Haar QC, 19 May 2021) Roger ter Haar QC held that the referring party should pay the adjudicator's fees.
Roger ter Haar QC held that the referring party should pay the adjudicator's fees in this situation on the basis that (i) The adjudicator's resignation was an error on his part but did not represent an abandonment of his appointment or a deliberate and impermissible refusal to provide a decision (ii) The adjudicator on the true construction of his standard terms was entitled to be paid for the work done by him in the absence of any bad faith on his part by resigning and (iii) The terms satisfied the requirement of reasonableness in the Unfair Contract Terms Act.
The judge stated that the adjudicator took the view that it was clear that the underlying contract was between the referring party and Ms Patel and not between it and the responding party. If that was the correct view, then, as the referring party accepted, the adjudicator was correct in deciding that he had no jurisdiction over the dispute. On the evidence the adjudicator, at the lowest, was entitled to conclude that the contract was with Ms Patel and not the responding party. The referring party's characterisation of the adjudicator's decision to resign as an "abandonment of his appointment and a deliberate and impermissible refusal to provide a decision" should be rejected. Resignation by an adjudicator is not of itself a breach of the terms of the adjudicator's engagement since paragraph 9(1) of the Scheme permits the adjudicator to resign at any time on giving notice to the parties.
Clause 1 of the adjudicator's terms provided that: "The Parties agree jointly and severally to pay the Adjudicator's fees and expenses as set out in this Schedule. Save for any act of bad faith by the Adjudicator, the Adjudicator shall also be entitled to payment of his fees and expenses in the event that the Decision is not delivered and/or proves unenforceable." The judge went on to state that it was not desirable to discuss at any length the limits of "bad faith" in construing a clause such as clause 1. It was sufficient to say that a situation such as this where an adjudicator acting with diligence and honesty comes to the conclusion that the proper course is for him to exercise his right under paragraph 9(1) of the Scheme to resign is not a situation within the expression "bad faith". Accordingly his conclusion was that on the true construction of his terms and conditions, the adjudicator was entitled to be paid for the work done by him
The full text of the judgment of Roger Ter Haar QC
There is before me an application on the part of the Claimant for summary judgment for the fees of Mr. Nigel Davies for acting as the Adjudicator in an Adjudication brought by the Defendant against Bhavishya Investment Ltd ("BIL").
Although Mr Davies was the Adjudicator, his fees, if payable, were payable to the Claimant. Hereafter I refer to Mr Davies as "the Adjudicator" save where I am recording submissions he made before me as representative of the Claimant.
The claim (in the sum of £4,290 plus VAT) is for a very small amount of money by the standard of claims which come before this Court. It raises interesting points as to the circumstances in which an Adjudicator's fees are or are not payable.
The Facts
In late 2019 early 2020 the Defendant carried out construction operations at a restaurant called "Funky Brownz", 28 Belmont Circle, Kenton Lane, Stanmore, Middlesex (the Premises).
The Premises are owned and operated by BIL as "Funky Brownz".
At all material times one Ms Vaishali Patel was a director and the majority shareholder in BIL.
In late 2019 a set of contract documents was drawn up but not signed.
At the head of the proposed contract is a section which reads as follows:
"CLIENT
VAISHALI PATEL
FUNKY BROWNZ
28 Belmont Circle, Belmont
Circle Kenton Lane
Stanmore, Middlesex, United
Kingdom, HA3 8RF (the "Client")"
Clause 1 of the proposed contract provided:
"The Client hereby agrees to engage the Contractor to provide the Client with the following services (the "Services"):
DESIGN SUPPLY AND BUILD OF FUNKY BROWNZ 28 Belmont Circle, Belmont Circle Kenton Lane, Stanmore, Middlesex, United Kingdom, HA3 8RF, Internal decorations."
At the end of the proposed contract, it provided for a seal to be affixed:
"IN WITNESS WHEREOF the Parties have duly affixed their signatures under hand and seal on this ___ day of _______ ____
Client
FUNKY BROWNZ
Per ____________ (Seal)
Attention: OWNER/PROPITIER MISS VAISHALI PATEL."
(The mistyping of the word "Proprietor" is in the original.)
As I have said, the contract was never signed. Invoices for the works as they progressed were however addressed to and paid by BIL.
As at completion of the works in February 2020, the Defendant claimed an unpaid balance of £35,974.29.
The parties then fell into dispute about whether the works were complete, defects and snags.
It is the Defendant's case that it asked for access to carry out any works required in order to be paid. Access was finally secured on 18 May 2020. The Defendant said it completed the defects notified.
However, payment was still not made: it was claimed that the remedial works were defective and the works were still incomplete. These exchanges about access and defects took place between about April 2020 and at least June 2020 between solicitors for the Defendant and those representing Funky Brownz (I put it this way so as not to pre-judge who was the Defendant's counterparty).
The Defendant says that all of those communications were on the basis that BIL was the contracting party liable for any sums due. At no stage did BIL suggest that Ms Patel was personally liable instead.
On 15 April 2020 the Defendant served a Statutory Demand upon for the unpaid sums. The Statutory Demand was directed at BIL. Claims consultants engaged by BIL threatened an injunction to restrain presentation of a petition on the basis that the debt was bona fide disputed because of the defects, but not on the additional ground that BIL was not the relevant contracting party.
The Defendant therefore withdrew the Statutory Demand.
Under cover of an e-mail dated 14 September 2020, the Defendant's solicitors, Costigan King, submitted a request to The Royal Institution of Chartered Surveyors ("RICS") dated 14 September 2020 for the nomination of a construction adjudicator under the Scheme for Construction Contracts (England and Wales) Regulations 1998 SI No.649 (as amended) ("the Scheme") and the CIC Low Value Disputes Model Adjudication Procedure ("the Model Procedure") in relation to a dispute said to be with BIL. Costigan King then sent the Notice of Adjudication to BIL by e-mail of the same date.
On 15 September 2020 the Adjudicator was nominated by the RICS to act as the Adjudicator under the Scheme and the Model Procedure in relation to a dispute defined as being between the Defendant and BIL.
This was the first of two adjudications. The application before me concerns the second adjudication referred to below.
On the same date, 15 September, the Adjudicator wrote to the parties by post and e-mail providing directions and copies of his terms and conditions by letter. Costigan King acknowledged receipt of the letter and e-mail under cover of their e-mail of the following day, 16 September 2020.
I refer to the Adjudicator's terms and conditions in more detail below. They were the same in respect of both adjudications.
Neither party objected to those terms and conditions.
Under cover of an e-mail dated 21 September 2020 BIL disputed that the Adjudicator had jurisdiction to decide the dispute in the first adjudication on the grounds that the request for nomination of an adjudicator was made to the RICS before the Notice of Adjudication had been issued by the Defendant to BIL.
By email on 21 September 2020 the Adjudicator resigned as adjudicator in the first adjudication.
The Claimant rendered to the Defendant an invoice for 1.7 hours of the Adjudicator's time. The Defendant paid this invoice.
On behalf of the Defendant, Costigan King issued BIL with a second Notice of Adjudication dated 21 September 2020 and a second request to the RICS followed on 22 September 2020 for the nomination of a construction adjudicator under the Scheme and the Model Procedure.
On 23 September 2020 the Adjudicator was nominated again by the RICS to act as Adjudicator under the Scheme and the Model Procedure in relation to the same dispute between the Defendant and BIL.
Again, the Adjudicator wrote to the parties providing directions and copies of his terms and conditions by letter sent by post and e-mail dated 23 September 2020. His terms and conditions were identical to those which he had issued to the parties eight days earlier on 15 September 2020. Again, there was no objection to his terms and conditions.
The Adjudicator received the Response on 8 October 2020 and the Reply on 15 October 2020.
In his Skeleton Argument for the hearing before me, Mr Davies set out what happened next as follows:
The Response was received on 8 October 2020 and the Reply was received on 15 October 2020.
In accordance with Referral para.4 … the Defendant claimed the Parties to the adjudication had entered into "the Contract" pursuant to an agreement in writing on or around 21 November 2019.
The Contract the Defendant had written and relied upon in order to bring the adjudication, unequivocally recorded that it was between the Defendant and Miss Vaishali Patel and it contained both a "Modification of Agreement" clause at para.24 and at para.27 an "Entire Agreement" clause ... Despite exhaustive enquiries of the documents and of the Parties as per my e-mail dated 16 October 2020 timed 1759hrs. I established that the Contract had not ever changed (e.g. by novation) and remained to be between the Defendant and Miss Patel.
Para.12(b) of Part 1 of the Scheme provides that I was to avoid incurring unnecessary expense. Following e-mail correspondence with the Parties dated 15 and 16 October 2020 consistent with para.9 of Part 1 of the Scheme and para.31 of the CIC LVD MAP I resigned as the Adjudicator by e-mail dated 16 October 2020 timed 1759hrs. I resigned because Bhavishya was not a Party to and/or identified within the Contract on which basis the second adjudication had been referred and therefore I was without jurisdiction as per paragraph 31 in Dacy Building Services Ltd v IDM Properties LLP [2016] EWHC 3007 (TCC) (25 November 2016) and paragraphs 62 to 64 of the judgment in M Hart Construction Ltd & Anor v Ideal Response Group Ltd (Rev 1)[2018] EWHC 314 (TCC) (07 March 2018).
Clearly, I could not issue a Decision in relation to the contractual rights of one of the contracting parties in an adjudication where the other contracting party was not a party to the process. Obviously, Bhavishya's participation did not change this.
It had been necessary to establish such facts because at Referral para.39 the Defendant had requested that I provide written reasons for my Decision and because it was a critical component to my reasoning. It was a natural consequence of establishing whether and on what basis the Defendant was entitled to the payment it claimed from Bhavishya, all in accordance with para.13 of Part 1 of the Scheme i.e. take the initiative in ascertaining the facts and the law necessary to determine the dispute. It was part of the process of determining the adjudication as per paragraph 38 in Ex Novo Limited v MPS Housing Ltd [2020] EWHC 3804 (TCC) (17 December 2020).
I issued the Claimant's invoice number 696 in the VAT inclusive sum of £5,148 in accordance with my accepted terms and conditions addressed to the Defendant, by e-mail to Costigan King dated 19 October 2020 timed 1122hrs.
Under cover of my e-mail dated 21 October 2020 timed 1654hrs, I provided a breakdown of my time charged under invoice number 696 and out of the 16.9 hours spent I charged for 13.2 hours."
On 20 October 2020 Costigan King wrote by email to say that the Defendant would not pay the Claimant's invoice because it was claimed that Mr Davies had committed a repudiatory breach of his contract of appointment. The Defendant was said to have accepted the Adjudicator's repudiation so that his terms and conditions had ceased to have effect. It was also claimed that the Claimant was not entitled to payment because of the Court of Appeal decision in PC Harrington Contractors Limited v Systech International Limited [2012] EWCA Civ 1371.
The Adjudicator's Terms and Conditions
The covering letters to the Adjudicator's two appointments made clear that any fees charged would be paid through the Claimant company.
The following were the material provisions of the Adjudicator's terms and conditions:
"Basis of Charge
Time related for hours expended working or travelling in connection with the Adjudication including all time up to settlement of any Fee Invoice, which, for the avoidance of doubt, may include any time including Court time, spent securing payment of any fees, expenses and disbursements due.
Amount of Charge
The Adjudicator's (Nigel J. Davies) fee shall be charged in accordance with the CIC LVD MAP current as at the date of this letter as set out in Schedule 1 thereto. Should the said CIC LVD MAP cease to apply then the amount of charge for the Adjudicator shall be £325 per hour applied on an ab initio basis, i.e. it will be applied from the date of the Adjudicator's nomination by the RICS.
In any event the CIC LVD MAP shall no longer apply from the point at which a CIC LVD MAP Decision is delivered and thereafter the £325 per hour charge shall apply, e.g. in relation to securing unpaid fees, expenses and disbursements due.
Frequency of Charge
A Fee Invoice will be raised and is due for payment 7 days thereafter.
In the event of the Adjudication ceasing for any reason whatsoever prior to a Decision being reached, a Fee Invoice will be raised immediately and is due for payment 7 days after the date of the Invoice.
In the event of any invoice not being settled as stated an additional charge may be raised for interest charges, which charges will be calculated at the rate of 2.5% per calendar month or pro-rata any part thereof, for the period between the date of invoice and the date of payment in full of that invoice.
Miscellaneous Provisions:
- The Parties agree jointly and severally to pay the Adjudicator's fees and expenses as set out in this Schedule. Save for any act of bad faith by the Adjudicator, the Adjudicator shall also be entitled to payment of his fees and expenses in the event that the Decision is not delivered and/or proves unenforceable.
- The Parties acknowledge that the Adjudicator shall not be liable for anything done or omitted in the discharge or purported discharge of his functions as Adjudicator (whether in negligence or otherwise) unless the act or omission is in bad faith, and any employee or agent of the Adjudicator shall be similarly protected from liability.
- The Adjudicator is appointed to determine the dispute or disputes between the Parties and his decision may not be relied upon by third parties, to whom he shall owe no duty of care.
The Scheme
The statutory scheme for adjudication is contained in the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998 No. 649) as amended.
Paragraph 9 provides:
"(1) An adjudicator may resign at any time on giving notice in writing to the parties to the dispute.
(2) An adjudicator must resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that adjudication.
(3) Where an adjudicator ceases to act under paragraph 9(1)"
(a) the referring party may serve a fresh notice under paragraph 1 and shall request an adjudicator to act in accordance with paragraphs 2 to 7; and
(b) if requested by the new adjudicator and insofar as it is reasonably practicable, the parties shall supply him with copies of all documents which they had made available to the previous adjudicator.
(4) Where an adjudicator resigns in the circumstances referred to in paragraph (2), or where a dispute varies significantly from the dispute referred to him in the referral notice and for that reason he is not competent to decide it, the adjudicator shall be entitled to the payment of such reasonable amount as he may determine by way of fees and expenses reasonably incurred by him. Subject to any contractual provision pursuant to section 108A(2) of the Act, the adjudicator may determine how the payment is to be apportioned and the parties are jointly and severally liable for any sum which remains outstanding following the making of any such determination."
Paragraph 11 provides:
(1) The parties to a dispute may at any time agree to revoke the appointment of the adjudicator. The adjudicator shall be entitled to the payment of such reasonable amount as he may determine by way of fees and expenses incurred by him. Subject to any contractual provision pursuant to section 108A(2) of the Act, the adjudicator may determine how the payment is to be apportioned and the parties are jointly and severally liable for any sum which remains outstanding following the making of any such determination.
(2) Where the revocation of the appointment is due to the default or misconduct of the adjudicator, the parties shall not be liable to pay the adjudicator's fees and expenses."
Paragraph 12 provides:
"The adjudicator shall
(a) act impartially in carrying out his duties and shall do so in accordance with any relevant terms of the contract and shall reach his decision in accordance with the applicable law in relation to the contract; and
(b) avoid incurring unnecessary expense."
Paragraph 13 provides:
"The adjudicator may take the initiative in ascertaining the facts and the law necessary to determine the dispute, and shall decide on the procedure to be followed in the adjudication."
Paragraph 20 provides:
"The adjudicator shall decide the matters in dispute. He may take into account any other matters which the parties to the dispute agree should be within the scope of the adjudication or which are matters under the contract which he considers are necessarily connected with the dispute."
Paragraph 25 provides:
"The adjudicator shall be entitled to the payment of such reasonable amount as he may determine by way of fees and expenses reasonably incurred by him. Subject to any contractual provision pursuant to section 108A(2) of the Act, the adjudicator may determine how the payment is to be apportioned and the parties are jointly and severally liable for any sum which remains outstanding following the making of any such determination."
Paragraph 26 provides:
"The adjudicator shall not be liable for anything done or omitted in the discharge or purported discharge of his functions as an adjudicator unless the act or omission is in bad faith, and any employee or agent of the adjudicator shall be similarly protected from liability."
PC Harrington Contractors Limited v Systech International Limited
In any dispute concerning whether an adjudicator is entitled to his or her fees, the starting point is almost always the Court of Appeal decision in PC Harrington Contractors Ltd v Systech International Ltd [2012] EWCA Civ 1371; [2013] Bus LR 970; [2013] BLR 1.
In PC Harrington the adjudicator was found in each of three references to have reached a conclusion in breach of his duty to comply with the rules of natural justice in that he failed to decide a relevant issue raised by way of defence because he took what was later held to have been an erroneous view as to jurisdiction. The consequence was that the decisions were unenforceable.
The question which arose was whether the adjudicator was entitled to his fees for producing unenforceable decisions. At first instance Akenhead J. decided that he was. The Court of Appeal took the opposite view and allowed an appeal.
In his judgment the Master of the Rolls said this:
"[32] I return to the question: what was the bargained-for performance? In my view, it was an enforceable decision. There is nothing in the contract to indicate that the parties agreed that they would pay for an unenforceable decision or that they would pay for the services performed by the adjudicator which were preparatory to the making of an unenforceable decision. The purpose of the appointment was to produce an enforceable decision which, for the time being, would resolve the dispute. A decision which was unenforceable was of no value to the parties. They would have to start again on a fresh adjudication in order to achieve the enforceable decision which Mr Doherty had contracted to produce.
[33] Para 11(2) of the Scheme provides powerful support for PCH's case. If the adjudicator's appointment is revoked due to his default or misconduct, he is not entitled to any fees. It can hardly be disputed that the making of a decision which is unenforceable by reason of a breach of the rules of natural justice is a "default" or "misconduct" on the part of an adjudicator. It is a serious failure to conduct the adjudication in a lawful manner. If during the course of an adjudication, the adjudicator indicates that he intends to act in breach of natural justice (for example, by making it clear that he intends to make a decision without considering an important defence), the parties can agree to revoke his appointment. In that event, the adjudicator is not entitled to any remuneration. It makes no sense for the parties to agree that the adjudicator is not entitled to be paid if his appointment is revoked for default or misconduct before he makes his purported decision, but to agree that he is entitled to full remuneration if the same default or misconduct first becomes manifest in the decision itself. I would not construe the agreement as having that nonsensical effect unless compelled to do so by express words or by necessary implication. I can find no words which yield such a meaning either expressly or by necessary implication.
[34] The fact that the adjudicator was not liable for anything done or omitted to be done unless it was in bad faith (para 26) lends further support to the view that the parties did not intend that the adjudicator should be paid for producing an unenforceable decision. If Miss Rawley is right, the adjudicator was entitled to be paid the same fee for producing an unenforceable decision as for producing one that was enforceable and yet, absent bad faith, the parties are not able to claim damages for the adjudicator's failure to produce an enforceable decision, regardless of the seriousness of the failure and the loss it has caused. That is a most surprising bargain for the parties to have made. I would be reluctant to impute to them an intention to make such a bargain unless compelled to do so. I can find nothing in the terms of engagement or the Scheme which compels the conclusion that this was their intention.
The position of judges and arbitrators
[35] As I have said, the judge seems to have found support for his conclusion that the functions performed by an adjudicator which are ancillary and anterior to the making of a decision are valuable in their own right by comparing the position of adjudicators with that of arbitrators and judges: see para 12 above. Miss Rawley has not relied on this part of the judge's reasoning. I think that she is right not to do so. A judge has an inherent jurisdiction and does not derive his powers over a dispute from a contract of appointment. That is sufficient to render any comparison with a judge wholly inapposite.
[36] At first sight, the comparison with the position of arbitrators might seem to be more fruitful, since they derive their authority from a contract with the parties. But as Mr Bowling points out, there are important differences between adjudicators and arbitrators. First and foremost, serious errors and fundamental misunderstandings by an arbitrator do not invalidate his award. The award is binding, subject to the supervisory jurisdiction of the court under sections 66-68 of the Arbitration Act 1996. Secondly, when anterior and ancillary functions are carried out by an arbitrator, they are binding on the parties (and therefore the arbitrator gives value in performing them). If the arbitrator ceases to hold office during the course of a reference, the parties are free to agree whether and, if so, how the vacancy is to be filled and whether and, if so, to what extent the previous proceedings should stand: see section 27 of the Act. This is to be contrasted with the position in an adjudication: if the adjudicator's appointment is terminated (for whatever reason), the process must be started again with a fresh referral. Thirdly, an arbitrator has inherent jurisdiction and power to make a binding decision on the scope of his own jurisdiction, unless the parties otherwise agree: section 30 of the Act. An arbitrator, unlike an adjudicator, can give value by providing a binding ruling on his jurisdiction.
Policy considerations
[37] Finally, I should deal briefly with the judge's recourse to policy considerations. I accept that the statutory provisions for adjudication reflect a Parliamentary intention to provide a scheme for a rough and ready temporary resolution of construction disputes. That is why the courts will enforce decisions, even where they can be shown to be wrong on the facts or in law. An erroneous decision is nevertheless an enforceable decision within the meaning of the 1996 Act and the Scheme. But a decision which is unenforceable because the adjudicator had no jurisdiction to make it or because it was made in breach of the rules of natural justice is quite another matter. Such a decision does not further the statutory policy of encouraging the parties to a construction contract to refer their disputes for temporary resolution by an adjudicator. It has quite the opposite effect. It causes the parties to incur cost and suffer delay on a futile exercise. I can see no basis for holding that Parliament must have intended that an adjudicator who produces an unenforceable decision should be entitled to payment. As I have attempted to show, Parliament did address the question of remuneration in the Scheme and produced a carefully calibrated set of provisions. I suppose that Parliament could have provided that an adjudicator was entitled to reasonable remuneration even where he produced an unenforceable decision, although this possibility seems rather fanciful to me. But it did not do so. I do not consider that it is legitimate, in effect, to rewrite the Scheme on the basis of some unarticulated Parliamentary policy grounds."
In his judgment, Davis L.J. said:
"[40] In the present case, as Akenhead J found at the earlier hearing, the adjudicator albeit acting in good faith entirely failed to deal with a defence raised which (if valid, which it may or may not have been) would have defeated Tyroddy's claims. Further, he failed first to advise the parties of his intended approach or seek their submissions. So it can properly be said that there was here a breach of the rules of natural justice constituting a "default" of which he was the author. But it will not always be so. For example, the logic of Mr Bowling's argument would, as he accepted, apply absent specific contractual terms to the contrary to cases where, for example, an adjudicator, having done a considerable amount of work, died or was struck down with serious incapacitating illness before a decision could be produced at all.
[41] That said, in my view the key nevertheless is to consider what was the contractual bargain actually made. To say in general terms, as Mr Bowling did as an opening observation, that the law does not require people to pay for worthless things is not necessarily right as a generalisation and is wrong in failing to focus on what the actual terms of the contract are. I in fact did not regard either counsel's respective appeals to the asserted merits very helpful. All depends on the contract actually made.
[42] To me, what effectively decides the matter in favour of the appellant are the terms of the Scheme itself. As the Master of the Rolls has explained, the terms of paragraph 9 and of paragraph 11 and in particular the intention behind and implications of paragraph 11(2) indicate that the conclusion for which Mr Bowling contended is the correct one. Nor do the Terms of Engagement employed by Mr Doherty and incorporated into this particular contract indicate any different conclusion.
[43] I also would attach significant weight to paragraph 20 of the Scheme. That expressly stipulates that the adjudicator shall decide the matters in dispute. But where, as here, an adjudicator delivers a decision which is entirely unenforceable then he will not have decided the matters in dispute. On Miss Rawley's argument the parties absent an express term not only have no redress for any loss (in that the Scheme excludes any warranty on the part of the adjudicator and excludes any liability for acts done or omitted, absent bad faith) they also must pay the adjudicator's fees notwithstanding that the adjudicator has not decided the matters in dispute. In my view, that would be surprising and is also an indicator in favour of Mr Bowling's argument.
[44] As to the special situation arising in an adjudication where one of the parties raises a challenge on jurisdiction before a decision is reached and then, having received the adjudicator's ruling on jurisdiction, elects that the adjudicator should proceed to a decision, that situation is in my view correctly addressed by Ramsey J at paragraphs 76 to 79 of his judgment in Linnett v Halliwells LLP [2009] EWHC 319 (TCC), [2009] BLR 312. The adjudicator's fees are then subject of course to any express terms agreed payable even if the Court subsequently were to declare the initial challenge to the jurisdiction to have been well-founded.
[45] I therefore would conclude in the present case that the adjudicator is not entitled to be paid any fees. He has not produced an (enforceable) decision which determines the matters in dispute: which is what this contract required of him before his entitlement to fees arose.
[46] I doubt if the present decision should have any very great ramifications. Prior to this case, I personally had had little acquaintance with the adjudication Scheme under the 1996 Act. It appears, from what we were told, generally to be working very well indeed and not least, I suspect, because of the short prescribed time limits and the splendid "pay now, argue later" approach, which is thoroughly to be commended. At all events in the fifteen years or so since the scheme has been operating this particular kind of dispute about fees seems, as we were told, not previously to have surfaced in the courts. In any case, if this decision does give rise to concerns on the part of adjudicators then the solution is in the market-place: to incorporate into their Terms of Engagement (if the parties to the adjudication are prepared to agree) a provision covering payment of their fees and expenses in the event of a decision not being delivered or proving to be unenforceable. It is of course a consequence of this court's conclusion that it is for the adjudicator to stipulate for such a term: not for the parties to the adjudication to stipulate to the contrary."
Mr Davies told me that the terms and conditions upon which the Claimant relies were drafted in the light of Davis L.J.'s judgment.
The Issues before the Court
In his skeleton argument, Mr Bowling, for the Defendant, identifies the issues before the Court as follows:
1. Whether there was a threshold point of jurisdiction before the Adjudicator pursuant to which he was entitled to resign, or whether the Adjudicator's decision to do so represented abandonment of his appointment and a deliberate and impermissible refusal to provide a Decision.
2. The proper construction of the following clauses in the Adjudicator's standard terms, which the Adjudicator claims entitle him to payment for work done to the point of abandonment, the lack of a Decision notwithstanding:
- Clause 1 of the Adjudicator's standard terms ("Save for any act of bad faith by the Adjudicator, the Adjudicator shall be entitled to payment of his fees and expenses in the event that the Decision is not delivered and/or proves unenforceable"); and
- The unnumbered clause stating that "In the event of the Adjudication ceasing for any reason whatsoever prior to a Decision being reached, a Fee Invoice will be raised immediately and [become] due for payment"
If those clauses are effective in the manner the Adjudicator contends, whether they are nevertheless void under s3(2)(b) of the Unfair Contract Terms Act 1977.
If a fee is payable, whether 13.20hrs is excessive given the amount of work done on the application of Fenice Investments v Jerram Falkus Construction [2011] EWHC 1678 (TCC).
Issue No. 1: Was there a threshold jurisdictional issue?
The Adjudicator took the view that it was clear that the underlying contract was between the Defendant and Ms Patel, not between the Defendant and BIL.
If that was the correct view, then, subject to waiver on the part of BIL, the Adjudicator was correct in deciding that he had no jurisdiction over the dispute: Dacy Building Services Ltd v IDM Properties Ltd [2016] EWHC 3007 (TCC); [2017] BLR 114 and M Hart Construction Ltd & Anor v Ideal Response Group Ltd [2016] EWHC 3007 (TCC).
To that extent, I did not understand Mr Bowling to dissent. However he submitted, firstly, that the preponderance of evidence showed that BIL, rather than Ms Patel, was the contracting party.
I do not accept this first argument. The Referral clearly placed the case upon the basis that the contract was a contract in writing. Whilst the proposed contract was unsigned, it clearly envisaged that the contract would be between the Defendant and Ms Patel. I also note that the Defence in this action did not contend that the construction contract was with BIL.
On the evidence before him, it seems to me at the lowest the Adjudicator was entitled to conclude that the contract was with Ms Patel, not BIL.
Secondly Mr Bowling argues that in any event, there was submission to the jurisdiction by BIL. By paragraphs 4 11 of the Referral SCS made a clear allegation that the construction contract was with BIL. The Response did not dispute that, concentrating on BIL's allegations of defects in the works provided to it, together with BIL mounting a counterclaim for some £82,768.20. Mr Bowling submits that the submission of a Response in these terms amounted to a clear waiver of any threshold jurisdictional point based on an allegation that the contract was with Ms Patel instead; see Brims v A2M [2013] EWHC 3262 (TCC) and Thomas-Fredric's (Construction) Limited v Keith Wilson [2004] BLR 24 per Simon Brown LJ at [31].
In my view, based upon those decisions, it was probably the case that if after the Adjudicator had issued a decision, BIL were to suggest that the Adjudicator did not have jurisdiction to issue that decision upon the basis that BIL was a not a party to the contract, BIL would be held to have waived the right to pursue such a jurisdictional argument.
Developing that argument, Mr Bowling says that to the extent that a party does not adopt a jurisdictional issue (such as there may be) a fortiori it is not open to the Adjudicator to decline jurisdiction. The Adjudicator's power to take the initiative to ascertain the facts and the law (Scheme Part I para 13) is obviously to be exercised in the context of the dispute the parties empower the Adjudicator to decide. It is not a roving commission to identify, formulate and decide the reference on the basis of new and fundamental issues neither party raises nor adopts despite invitation.
I do not find this an easy point. It is undoubtedly the case that the Adjudicator has power to take the initiative, and that in this case the Adjudicator believed that he was exercising that power. Further, I accept that the Adjudicator believed that to take the initiative was consistent with his duty under paragraph 12 of the Scheme to avoid unnecessary expense.
In my judgment it would have been wiser for the Adjudicator not only to inquire as to the parties' position as to who were the contracting parties, but also to inquire in terms as to whether both parties accepted that he had jurisdiction. However he did not do that.
The effect of what the Adjudicator did was to deprive the parties of an answer to their differences as to what sum was payable (either by Ms Patel or by BIL) in respect of the project. However it is fair to say that BIL never showed any enthusiasm for this dispute to be aired.
The conclusion to which I have come is that the route which the Adjudicator took was outside the ambit of paragraph 13 of the Scheme: that paragraph entitles the Adjudicator to investigate matters "necessary to determine the dispute", which necessarily involves the question, what is the dispute? At the time when the Adjudicator resigned, there was no dispute either as to the identity of the contracting parties or as to his jurisdiction.
Accordingly, in my view the Adjudicator's reasoning in deciding to resign on the basis that he had no jurisdiction when that was not an issue which the parties had referred to him was erroneous.
However, that is not an end of the matter. It is necessary to consider whether the Adjudicator was nevertheless entitled to the fees claimed.
It is submitted by Mr Bowling that the Adjudicator's decision to resign "represented abandonment of his appointment and a deliberate and impermissible refusal to provide a Decision."
I do not accept that characterisation of what the Adjudicator did. Far from "abandoning his appointment", the Adjudicator acted in accordance with what he regarded as being his duty. Far from there being a "deliberate and impermissible refusal to provide a Decision", the Adjudicator resigned upon the basis that it was not open to him to reach a Decision in a dispute between the Defendant and BIL of the rights and obligations of a contract between the Defendant and Ms Patel. That is very far from being a "deliberate and impermissible refusal to provide a Decision".
Further, resignation by an Adjudicator is not of itself a breach of the terms of the Adjudicator's engagement since paragraph 9(1) of the Scheme permits the Adjudicator to resign at any time on giving notice to the parties: the question here is whether upon resigning the Adjudicator was still entitled to his fees.
In my judgment the answer to that question turns upon the true construction of the Adjudicator's terms and conditions.
Issue No. 2: the effect of the Adjudicator's Terms and Conditions
The first relevant provision is in the section headed "Frequency of Charge":
"In the event of the Adjudication ceasing for any reason whatsoever prior to a Decision being reached, a Fee Invoice will be raised immediately and is due for payment 7 days after the date of the Invoice."
On its face, this provision would entitle the Adjudicator to receive fees whenever the adjudication cessed, even if it ceased in circumstances where the Adjudicator was acting in bad faith. That would be a strange conclusion particularly given the terms of Clauses 1 and 3. In my judgment this clause should not be construed as entitling the Adjudicator to fees where no fees would be payable under Clause 1. This clause is in a section headed "frequency of charge", and I read the sentence I have set out in the previous paragraph as being concerned with the timing of an invoice and payment.
As I have already set out, Clause 1 provides:
"The Parties agree jointly and severally to pay the Adjudicator's fees and expenses as set out in this Schedule. Save for any act of bad faith by the Adjudicator, the Adjudicator shall also be entitled to payment of his fees and expenses in the event that the Decision is not delivered and/or proves unenforceable."
Mr Bowling draws attention to the word "also" in the second sentence of this Clause. He distinguishes this case from cases such as those where an Adjudicator issues an unenforceable decision or produces a decision but fails to deliver it in time. Here, he says, the Adjudicator at one and the same time managed to abdicate his responsibility, exceeded his jurisdiction and failed to exhaust it. He says that this is a situation or a congeries of situations to which Clause 1 does not apply.
I do not agree with this submission: in my judgment the Clause means that in addition to being paid for producing a Decision (which is the normal event upon the occurrence of which an Adjudicator is entitled to payment) the Adjudicator is entitled to be paid his fees for work done unless there has been an act of bad faith on the Adjudicator's part.
Mr Bowling's next submission focuses on the meaning of the phrase "bad faith". He submits that this should be construed as meaning "misconduct", that is to say a situation where the Adjudicator acts in a manner which is commercially improper and which doesn't honour or maintain fidelity to the bargain the Adjudicator has struck with the parties.
In support of that submission he cites the decision of Leggatt J., as he then was, in Yam Send Pte Limited v International Trade Corporation Limited [2013] EWHC 111 (QB); [2013] 1 Lloyd's Rep 526:
"[134] Importantly for present purposes, the relevant background against which contracts are made includes not only matters of fact known to the parties but also shared values and norms of behaviour. Some of these are norms that command general social acceptance; others may be specific to a particular trade or commercial activity; others may be more specific still, arising from features of the particular contractual relationship. Many such norms are naturally taken for granted by the parties when making any contract without being spelt out in the document recording their agreement.
[135] A paradigm example of a general norm which underlies almost all contractual relationships is an expectation of honesty. That expectation is essential to commerce, which depends critically on trust. Yet it is seldom, if ever, made the subject of an express contractual obligation. Indeed if a party in negotiating the terms of a contract were to seek to include a provision which expressly required the other party to act honestly, the very fact of doing so might well damage the parties' relationship by the lack of trust which this would signify.
[136] The fact that commerce takes place against a background expectation of honesty has been recognised by the House of Lords in HIH Casualty v Chase Manhattan Bank [2003] 2 Lloyd's Rep 61. In that case a contract of insurance contained a clause which stated that the insured should have "no liability of any nature to the insurers for any information provided". A question arose as to whether these words meant that the insured had no liability even for deceit where the insured's agent had dishonestly provided information known to be false. The House of Lords affirmed the decision of the courts below that, even though the clause read literally would cover liability for deceit, it was not reasonably to be understood as having that meaning. As Lord Bingham put it at [15]:
"Parties entering into a commercial contract will assume the honesty and good faith of the other; absent such an assumption they would not deal."
To similar effect Lord Hoffmann observed at [68] that "parties contract with one another in the expectation of honest dealing", and that:
"in the absence of words which expressly refer to dishonesty, it goes without saying that underlying the contractual arrangements of the parties there will be a common assumption that the parties involved will behave honestly."
[137] As a matter of construction, it is hard to envisage any contract which would not reasonably be understood as requiring honesty in its performance. The same conclusion is reached if the traditional tests for the implication of a term are used. In particular the requirement that parties will behave honestly is so obvious that it goes without saying. Such a requirement is also necessary to give business efficacy to commercial transactions.
[138] In addition to honesty, there are other standards of commercial dealing which are so generally accepted that the contracting parties would reasonably be understood to take them as read without explicitly stating them in their contractual document. A key aspect of good faith, as I see it, is the observance of such standards. Put the other way round, not all bad faith conduct would necessarily be described as dishonest. Other epithets which might be used to describe such conduct include "improper", "commercially unacceptable" or "unconscionable".
[139] Another aspect of good faith which overlaps with the first is what may be described as fidelity to the parties' bargain. The central idea here is that contracts can never be complete in the sense of expressly providing for every event that may happen. To apply a contract to circumstances not specifically provided for, the language must accordingly be given a reasonable construction which promotes the values and purposes expressed or implicit in the contract. That principle is well established in the modern English case law on the interoperation of contracts: see e.g. Rainy Sky SA v Kookmin Bank [2011] 1 WLR 2900; Lloyds TSB Foundation for Scotland v Lloyds Banking Group Plc [2013] UKSC 3 at [23, [45] and [54]. It also underlies and explains, for example, the body of cases in which terms requiring cooperation in the performance of the contract have been implied: see Mackay v Dick (1881) 6 App Cas 251, 263; and the cases referred to in Chitty on Contracts (31st Ed), Vol 1 at paras 13-012 13-014."
Mr Bowling submits that the Adjudicator decided he was not going to decide the dispute which he had agreed to decide, and thus was not faithful to the bargain he had struck to act as Adjudicator.
In my view this argument bears considerable similarity to the argument which Mr Bowling successfully made to the Court of Appeal in PC Harrington v Systech. In that case the argument was that by coming to an erroneous view as to his jurisdiction to determine certain issues, the Adjudicator placed himself in a position where he delivered unenforceable decisions: in those circumstances, it was held that he was not entitled to recover his fees.
In that case, Davis L.J. suggested at paragraph [46] that the problem faced by an adjudicator in such a circumstance could be avoided be suitable terms in his contract of engagement:
"In any case, if this decision does give rise to concerns on the part of adjudicators then the solution is in the market-place: to incorporate into their Terms of Engagement (if the parties to the adjudication are prepared to agree) a provision covering payment of their fees and expenses in the event of a decision not being delivered or proving to be unenforceable. It is of course a consequence of this court's conclusion that it is for the adjudicator to stipulate for such a term: not for the parties to the adjudication to stipulate to the contrary."
I do not think it desirable in this case, where I have heard argument limited to the facts of this particular case, to discuss at any length the limits of "bad faith" in construing a clause such as Clause 1. It is sufficient for me to say that a situation such as this where an Adjudicator acting with diligence and honesty comes to the conclusion that the proper course is for him to exercise his right under Paragraph 9(1) of the Scheme to resign is not a situation within the expression "bad faith".
Accordingly, my conclusion is that on the true construction of his terms and conditions, the Adjudicator was entitled to be paid for the work done by him, subject to the application of the Unfair Contract Terms Act 1977 ("UCTA"), to which I refer below.
Before moving to the application of UCTA, I should note another argument put forward on behalf of the Defendant: it is suggested that on analysis the parties revoked the Adjudicator's appointment. This seems to me simply wrong on the facts. His appointment as Adjudicator came to an end upon his resignation. Thereafter there was no extant appointment to revoke.
Unfair Contract Terms Act
The Defendant contends that if the clauses of his terms and conditions are to be construed in the manner the Adjudicator contends, they are void under section 3(2)(b) of UCTA in that they allow the Adjudicator to render performance substantially different from that contracted for. The clauses are in the Adjudicator's standard terms of business. The starting presumption therefore is that they are void; the Adjudicator can only rely on them if he can show they satisfy the test of reasonableness.
Section 3 of UCTA provides:
"(1) This section applies as between contracting parties where one of them deals on the other's written standard terms of business.
(2) As against that party, the other cannot by reference to any contract term
(a) when himself in breach of contract, exclude or restrict any liability of his in respect of the breach; or
(b) claim to be entitled
(i) to render a contractual performance substantially different from that which was reasonably expected of him, or
(ii) in respect of the whole or any part of his contractual obligation, to render no performance at all except in so far as (in any of the cases mentioned above in this subsection) the contract terms satisfies the requirement of reasonableness."
I have considerable doubt whether Clause 1 is caught by Section 3 of UCTA. Clause 1 is simply concerned with payment of the Adjudicator's fees. It says nothing about what contractual performance the Adjudicator is expected to perform. In any event, paragraph 9(1) of the Statutory Scheme gives the Adjudicator an unfettered right to resign which is relevant to the contractual performance that the Adjudicator is expected to perform.
If I am wrong as to the application of section 3, I have no hesitation in holding that Clause 1 satisfied the requirement of reasonableness in UCTA:
(1) The provision was drafted with the judgment of Davis L.J. in mind and therefore in accordance with terms which the Court of Appeal regarded as being capable of being commercially acceptable – I put it that way because ultimately what is acceptable is a matter for the contracting parties;
(2) On Mr Bowling's submissions, the Adjudicator's terms are terms commonly found;
(3) There was no inequality of bargaining power;
(4) The Defendant could have rejected the terms (and sought a different adjudicator), but instead accepted them not once but twice: on each occasion the Defendant was represented by solicitors with enormous experience and expertise in respect of adjudications.
The Amount of the Fees
The Defendant disputes the amount of fees claimed.
Mr Davies said in his submissions that the hours charged were less than the number of hours actually expended.
I do not regard the amount charged as being excessive.
Conclusion
There will be judgment for the Claimant as sought.